Sub-Sahara Mining & Industrial Journal
Mining

Ivanhoe and JMMC making rapid progress at Kamoa-Kakula in DRC

At the Kamoa-Kakula Project in the Democratic Republic of Congo (DRC), the first phase of development at the Kakula Copper Mine is in many respects exceeding the published plans, says 39.6% owner and operator Ivanhoe Mines (Zijin Mining also has 39.6%). Crews now are mining and stockpiling development ore with an average grade greater than 8% copper. Almost all the underground development is in ore and, as a result, each blast in Kakula’s high-grade mining zone produces approximately 550 t of ore, which is transported to a dedicated, high-grade pre-production surface stockpile. Kakula’s high-grade ore stockpile is expected to total approximately 1.5 Mt prior to the start of initial production.

Underground development at Kakula is 4.2 km ahead of plan, helped in part by two new Sandvik Mining TH663i 63 t class underground trucks. More than 13.5 km of underground development is now complete, against the original plan of 9.3 km. The outstanding mining team has again broken the record of the previous 30 days and is on pace to set its third consecutive monthly development record with 1.7 km of advancement in April ─ 560 m ahead of plan. Approximately 29.5 km of underground development is scheduled for the remainder of 2020 and 2021 until scheduled first concentrate production. Development is carried out by JMMC, a DRC subsidiary of China’s leading contract miner JCHX Mining Management.

In parallel with the construction of Kamoa-Kakula’s phase 1 Kakula Mine, the independent Kakula definitive feasibility study (DFS) and an updated Integrated Development Plan for the entire Kamoa-Kakula mining complex also remain on schedule for Q3 2020. The Kakula DFS will provide a high level of accuracy for the project economics for Kakula’s initial phase of mine development, as most construction contracts and orders for significant capital items have been placed at fixed prices. The Integrated Development Plan will include details on the planned expansion phases for the greater Kamoa-Kakula mining complex; incorporating updates for mineral resources, production rates and economic analysis.

Related posts

Gov’t Orders Closure Of Gold Mining In Isiolo

Mining_Editor

Enaex is standardizing its products, making way for X-Booster®

Mining_Editor

Capital captures surface production drilling gig at AngloGold’s Geita

Mining_Editor

Leave a Comment